December Construction Update
December 12, 2024
Seasons greetings! As the year is drawing to a close, we’d like to celebrate the incredible year 2024 has been for Burnside Village, with another insight of the stage 6 construction progression.
To date we have accomplished a number of major construction milestones such as;
- Total Reo Supplied & Installed: 1747.486t, Total Concrete m3: 19,016.6m3, Over 2,000t of structural steel.
- 2 levels of Basement car-parking, welcoming 536 new spaces.
- The installation of 9 lifts, 4 travelators and 10 escalators.
- 365kW Solar system with opportunity for further expansion
As a project we have completed over;
728,702 hours, with 2837 Individuals Inducted and a peak of 422 on a single day!
We wish everyone a safe and relaxing holiday period, and are excited for all that 2025 will bring.