Key Construction Milestone Completion
August 13, 2024
Here’s a sneak peek into the behind-the-scenes drone footage of the Burnside Village Stage 6 construction progress over the last 3 months.
Key construction milestones:
– Nearing completion of the structural component of the 2000sqm custom Lanik roof with glazing to commence soon. The glass roof will be the crowning jewel of the Centre, providing an abundance of natural light.
– Level 1 concrete slab for the Food & Beverage, Home & Lifestyle and Fashion malls has been completed.
– Level 2 structure for the Leisure, Food & Beverage, Health/Wellness precinct is about to commence on the Western wing.
– Commencement of the skylight (skillion) structures in the common mall areas.
– Installation of the Level 1 and Level 2 escalators in the main atrium
– The project team have been working tirelessly to ensure a smooth construction process.
The countdown is on…